Water Network and House Connection Rehabilitation Scheme- Gaza and Northern Gaza Phase IV

Client / financing
Palestinian Water Authority (PWA)-Lyonnaise des Eaux / Khatib and Alami (LEKA)
Location
Palestine
Dates
2003
Water Supply, Transmission and Distribution

Water Network and House Connection Rehabilitation Scheme- Gaza and Northern Gaza Phase IV: The project included the design and preparing of tender documents for the rehabilitation of distribution networks in Gaza, Jabalia, and Beit Lahia. The project included the construction supervision on the installation of 225,160 and 110mm UPVC and 50mm MDPE pipes totaling to 90 km with all relevant house connections and fittings.