Projects / Housing and Public Buildings
Project Management & Engineering Supervision of Gaza Reconstruction Program for the Kuwait Government Grant for the Financing of Gaza Reconstruction in the State of Palestine ($200 M)
- Client / financing
- National Office for Gaza Reconstruction (NORG)
- Location
- Palestine
- Dates
- 2016–2019
Project Overview
The Gaza Reconstruction Program, funded by the Kuwait Government, aimed to alleviate the impact of the 2014 Israeli aggression on the Gaza Strip, with a total funding of $200 million. The program included projects across multiple sectors, such as housing, infrastructure, economic, agriculture, water, health, and education, targeting both reconstruction and infrastructure improvements in Gaza. The reconstruction efforts focused on restoring damaged facilities and improving the overall resilience of the region.
The scope covered reconstruction and rehabilitation in areas like housing (2,200 units), municipal and industrial infrastructure, agricultural facilities, health services, and education. A major project within the water sector included the construction of a main carrier line for drinking water, along with pumping stations and distribution networks to serve Gaza.
Role of CEP in the project
Description of Actual Services Provided:
Assist the concerned Ministries and authorities in preparing for the reconstruction program.
Review the design and tender documents including drawings, BOQs, specifications, etc.
Insure the completeness of tender documents of projects.
Monitor the bidding stage of the projects and preparation of evaluation reports.
Provide high-level supervision during the construction phase.
Verify the measurements of implemented works and the eligibility for payment.
Monitor the progress in the field and report periodically to the fund.
Review the Interim/Final payments submitted by Contractor/Suppliers and provide recommendation to the Ministerial Committee.
Other managerial and financial duties.
Management of the whole Kuwaiti Grant that included the following sectors:
Housing Sector (75 Million$): It included reconstruction about 2200 housing units that were destroyed in war 2014. The compensated area of the housing units ranged from 100 to 150 square meters.
Infrastructure Sector (35 Million$) with project in the 25 municipalities of Gaza: It was divided into the followings:
Infrastructure municipal projects (25 Million$).
Infrastructure projects for industrial areas (10 Million$).
Economic Sector (9.5 Million$): It was divided into the followings:
Reconstruction about 162 construction industrial facilities and 109 wooden industrial facilities that were destroyed in war 2014 (8.7 Million$).
Supply equipment for MoNE labs (0.8Million $).
Agriculture Sector (5 Million$): it was divided into the followings:
Reconstruction number of agricultural greenhouses (2.85 Million$).
Reconstruction number of livestock bins (1.25 Million$).
Construction of quarantine station (0.8 Million$).
Water Sector (60 Million$): Construction main carrier line for drinkable water characterized by the followings:
Capacity: 110 Million cubic meters.
Length: 20 km.
Diameter: 130 cm.
Distribution network length: 20 km.
Holding tanks for mixing and distribution: 7 tanks with capacity of 5,000 cubic meters.
Pumping stations: 6.
Monitoring and control network were included.
Health Sector (4 Million$): Reconstruction the Maternity Hospital in Al Shifa Medical Complex.
Education Sector (3Million$): It included a number of projects for educational NGOs and orphans centres. It was divided into the followings fields:
Construction new buildings or new stories.
Supply equipment for labs.
Road infrastructure assignments · 2016–2019
| # | Project Name | Length (m) | Municipality |
|---|---|---|---|
| Rehabilitation of Ahmed Fekri Street | 800 | Jabalia | |
| Development of Eastern Jabalia (Zaweya Street And Ajour Area) | 1300 | ||
| Development of Omar Bin El Khatab Area | 2500 | ||
| Paving of Internal Streets in Beit Lahia | 1700 | Beit Lahia | |
| Development of the Main Street of Bait lahia | 500 | ||
| Development of the Sea Street (Atatra-Americia) in Bait Lahia | 500 | ||
| Rehabilitation and Development of Al Sultan Abd El Hameed Street And Street #41 | 2200 | Beit Hanoun | |
| Rehabilitation and Development of the Industrial Zone | 700 | ||
| Rehabilitation and Development of Al Qaraman Street and Basel Naim Street | 1200 | ||
| Rehabilitation and Development of Khalil El Wazeer Street | 1400 | ||
| Maintenance of Internal Roads in Beit Hanoun | 1000 | ||
| Rehabilitation and Development of Abd El Dayem Area | 700 | ||
| Rehabilitation and Development of Al Banat Street and Mahdeya Shawa Area | 3800 | ||
| Rehabilitation of Internal Roads in Om El Nasser | 1100 | Om El Nasser | |
| Rehabilitation of Al Shaa'f Street | 2500 | Gaza | |
| Rehabilitation of Al Mansoura Street | 1000 | ||
| Maintenance of Al Muntar Street | 800 | ||
| Maintenance of Different Roads in Gaza | 700 | ||
| Development of Algeria Street | 800 | ||
| Rehabilitation of Industrial Zone Roads | 4000 | ||
| Rehabilitation of Northern Area | 1100 | Mughraqa | |
| Rehabilitation and Maintenance of the Main Road | 1100 | ||
| Rehabilitation and Maintenance of Al Seka Road | 900 | ||
| Rehabilitation and Maintenance of Street No. 16 | 400 | Al Zahra | |
| Rehabilitation of Internal Roads in Wadi Gaza | 1300 | Wadi Gaza | |
| Development of El Hadaba Area | 800 | Deir El Balah | |
| Development of Industrial Area Roads | 2400 | ||
| Maintenance of Internal Roads in Al Nuseirat | 800 | Nuseirat | |
| Rehabilitation of Omar Ben Abed El aziz Road | 1000 | Zawayda | |
| Development of Al Nuzha And El Salah Streets | 1000 | Bureij | |
| Development and Maintenance of Block 1 | 600 | Maghazi | |
| Rehabilitation of Street R1-8 | 800 | Musadar | |
| Pavement of Al Satari Street | 800 | Wadi El Salqa | |
| Rehabilitation of Main Roads in Khanyounis | 500 | Khanyounis | |
| Rehabilitation of Internal Roads in Khanyounis | 400 | ||
| Development of Street No. 3 | 300 | ||
| Development of Street No. 66 | 500 | ||
| Development of Street Nos. 101 and 106 – Industrial Zone | 1800 | ||
| Rehabilitation of Internal Roads in Al Qarara | 2400 | Qarara | |
| Rehabilitation of Al Shohada' Street | 1500 | Bani Suhaila | |
| Rehabilitation of Al Shohada' Street #18 | 1800 | Abasan El Kabira | |
| Pavement of Al Radwan Street | 700 | Abasan El Jadida | |
| Development of Internal Roads | 1000 | Khuza'a | |
| Development of Asphalt Roads – Abu Reida Area | 1800 | ||
| Development of Asphalt Roads – Radwan Area | 2000 | ||
| Development of Street #18 | 1600 | Fukhari | |
| Maintenance of Main Roads in Rafah | 1000 | Rafah | |
| Rehabilitation of "Abu Yusuf El Najar Hospital" Street | 700 | ||
| Development of Industrial Zone | 2000 | ||
| Rehabilitation of Destroyed Roads in Al Naser Area | 1000 | Naser | |
| Rehabilitation of Destroyed Roads in Al Shoka Area | 500 | Shoka |