Projects / Water Supply, Transmission and Distribution
Design Verification for Rehabilitation of Water Network in Different Areas in Khan Younis
- Client / financing
- American Near East Refugee Aid (ANERA) Financed through United States Agency for International Development (USAID)
- Location
- Palestine
- Dates
- 2022
Project Overview
This project focused on verifying the detailed design for the rehabilitation of approximately 20 km of water networks in various areas of Khan Younis, Gaza Strip. The objective was to ensure the accuracy and feasibility of the proposed design and prepare all necessary documents for the rehabilitation works, including detailed design and tender documents.
Role of CEP on the Project:
Reviewed the detailed design for the rehabilitation of the water network, ensuring it met local and international standards.
Verified the accuracy and feasibility of the rehabilitation plan, ensuring it complied with technical and regulatory requirements.
Prepared a complete set of detailed design documents and tender documents, including specifications, cost estimates, and timelines, to guide the tendering process and ensure a smooth execution of the project.

