Center for Engineering and Planning — CEP

Projects / Water Supply, Transmission and Distribution

Design of Al Qarara Water Tank (3000 m3), Booster Station and Carrier Water lines in Al Qarara Area

Client / financing
American Near East Refugee Aid (ANERA) Financed through United States Agency for International Development (USAID)
Location
Palestine
Dates
2016
Water Supply, Transmission and Distribution

Project Overview

This project focused on the design of a 3,000 m³ water tank, booster station, and 7.0 km of water carrier lines in Al Qarara Area, Khan Younis. The goal was to enhance the local water supply infrastructure and ensure efficient distribution to the community.

Role of CEP on the Project:

Designed the 3,000 m³ water tank, booster station, and 7.0 km of water carrier lines to meet local water supply needs.

Prepared complete tender documents, including technical specifications, cost estimates, and timelines to guide the procurement process.

Ensured the designs adhered to engineering standards and aligned with local infrastructure requirements.