Center for Engineering and Planning — CEP

Projects / Sewage Collection, Transmission, Treatment, Disposal and Reuse

Design of Wastewater Treatment Plant in Iraq

Client / financing
Ministry of Municipalities and Public Works (MMPW) - Republic of Iraq
Location
Iraq
Dates
2011–2012
Sewage Collection, Transmission, Treatment, Disposal and Reuse

Project Overview

This project involved the design of a sewage water treatment plant with an average flow capacity of 1,350 m³/hr, serving a population of approximately 1,300,000. The scope of work included preparing the required drawings and calculations for both civil and mechanical equipment necessary for the plant's construction and operation.

Role of CEP in the project

Developed the detailed design for the wastewater treatment plant, ensuring it met the required capacity of 1,350 m³/hr to effectively treat sewage water for a population of 1.3 million.

Prepared the necessary technical drawings, including layout plans, flow diagrams, and detailed civil and mechanical equipment specifications for the treatment plant.

Conducted calculations for the design of civil structures and mechanical systems, ensuring the plant's capacity and operational efficiency.

Coordinated with local authorities and stakeholders to ensure that the design complied with Iraq's regulatory standards and environmental requirements.

Provided comprehensive documentation for the tendering process, including equipment specifications and operational guidelines.