Projects / Sewage Collection, Transmission, Treatment, Disposal and Reuse
Re-Design and Prepare Tender Documents for Construction of Pumping Station No. 11 at Gaza Strip and Sewer Network in Tal El Hawa Area
- Client / financing
- Qatar Red Crescent
- Location
- Palestine
- Dates
- 2012
Project Overview
This project involved the re-design and preparation of tender documents for Pumping Station No. 11, the associated force main, and the sewer network in the Tal El Hawa area of Gaza City. The goal was to improve the wastewater management system in the region, ensuring effective sewage pumping and efficient distribution across the network.
Role of CEP in the project
Re-designed Pumping Station No. 11, including the force main and sewer network, to enhance the operational efficiency and capacity of the sewage system in Tal El Hawa.
Prepared detailed tender documents, including technical specifications, drawings, and schedules, to facilitate the construction process.
Ensured that the designs met local standards and were adaptable to the specific environmental and infrastructure needs of the Tal El Hawa area.
Provided technical input to ensure that the re-designed pumping station and sewer network were optimized for long-term performance and sustainability.